- Site: Sellafield
- IR number: 19-099
- Date: September 2019
- LC numbers: 36
Executive summary
Purpose of Intervention
The Office for Nuclear Regulation (ONR) undertakes all regulatory interaction with the Sellafield site licensee (Sellafield Limited (SL)) against a strategy defined by the ONR Sellafield, Decommissioning, Fuel and Waste (SDFW) Division. The planned inspection schedule for 2019/20 identifies the Licence Conditions (LCs) that will be inspected during this period.
The purpose of this inspection was for ONR to determine the adequacy of implementation of SL’s arrangements for compliance with LC 36 (“Organisational capability”). I focused on sampling evidence of compliance in the High Level Waste Plants (HLWP), which form part of SL’s Spent Fuel Management value stream, since the provision of adequate human resources is fundamental to the safe operation of these facilities and supports the delivery of the high hazard and risk reduction work by SL.
The overall adequacy of SL's site-wide LC 36 arrangements is considered separately in other ONR interventions.
Interventions Carried Out by ONR
Licence Condition 36 requires that the licensee provides and maintains adequate financial and human resources to ensure the safe operation of the licensed site.
I carried out a planned LC 36 compliance inspection of the HLWP facilities. My inspection focused on:
- SL’s nuclear baseline for the HLWP facilities (i.e. the means by which SL demonstrates the adequacy of its organisational structure, staffing and competencies to manage nuclear safety);
- The change process followed by the HLWP facilities when implementing changes to the organisational structure; and
- SL’s compliance with the licensee’s arrangements for determining, and ensuring compliance with, Minimum Safety Manning Levels (MSMLs) for the HLWP facilities.
The inspection comprised discussions with SL staff, review of records, and sampling of information contained within electronic databases and other documentation.
Explanation of Judgement if Safety System Not Judged to be Adequate
Not applicable since this was not a safety system based inspection.
Key Findings, Inspector's Opinions and Reasons for Judgements Made
No significant matters were identified as requiring immediate regulatory attention. My findings were shared with, and accepted by, SL as part of normal inspection feedback.
Conclusion of Intervention
On the basis of the evidence sampled at the time of the inspection, I judge that SL has adequately implemented its arrangements for LC 36 in the HLWP facilities. Noting the ONR guidance on inspection ratings, it is my opinion that an inspection rating of Green (no formal action) is merited here.