Control of radioactive materials and waste themed inspection

  • Site: Hunterston A
  • IR number: 21-032
  • Date: June 2021
  • LC numbers: 4, 5, 8, 25, 32, 34

Executive summary

Purpose of Intervention

These Licence Compliance Inspections were carried out as part of a series of planned inspections for the Hunterston A (HNA) decommissioning site during 2021/22.

Interventions Carried Out by ONR

I carried out a Themed Licence Compliance inspection on HNA’s Licence Condition (LC) 4, 5, 8, 25, 32, and 34 arrangements for control of radioactive materials and waste and their implementation. In addition, I held on-site meetings that included quarterly meetings with the HNA Safety Representatives, and meetings on progress with HNA’s decommissioning projects.

Explanation of Judgement if Safety System Not Judged to be Adequate

N/A.

Key Findings, Inspector's Opinions and Reasons for Judgements Made

From the documentation sampled and the areas inspected, I found that HNA’s implementation of their LC4, 5, 8, 25, 32 and 34 arrangements for the control of radioactive materials and waste was adequate.  

Conclusion of Intervention

I judged that HNA’s implementation of their LC4, 5, 8, 25, 32, and 34  arrangements for the control of radioactive materials and waste was adequate in the areas inspected and that during these inspections I did not identify any significant regulatory concerns.