- Site: Hinkley Point C
- IR number: 21-012
- Date: June 2021
- LC numbers: 19
Executive summary
Purpose of Intervention
In accordance with the Office for Nuclear Regulation’s (ONR’s) Hinkley Point C (HPC) Construction Inspection Plan, ONR performs a series of planned compliance inspections of applicable licence conditions. This is to ensure that the licensee, NNB Generation Company (HPC) Ltd (NNB GenCo), is adequately developing and implementing its compliance arrangements in a manner that is commensurate with the stage of the project under consideration.
This intervention was an inspection carried out to assess NNB GenCo’s compliance with licence condition 19 (LC19); Construction or Installation of New Plant. LC19 requires that where the licensee proposes to construct or install any new plant, which may affect safety, the licensee makes and implements adequate arrangements to control the construction or installation.
Intervention Aim
The aim of this intervention was to assess the adequacy of NNB GenCo’s construction management arrangements, together with its application of relevant good engineering practice, in the area of design substantiation, prefabrication and installation of the steel pool liner to the inner containment refuelling water storage tank (IRWST). This particular intervention has arisen as a result of NNB GenCo’s earlier notification to ONR that it was implementing a change to the originally conceived method of prefabrication and installation for the Unit 1 IRWST.
Explanation of Judgement if Safety System Not Judged to be Adequate
This section is not applicable as this was not a safety system inspection.
Key Findings, Inspector's Opinions and Reasons for Judgements Made
Responses to my questioning were forthcoming, informative, and provided me with confidence that the planned operations were being adequately managed with due consideration of the risks involved.
Overall, I was satisfied with the adequacy of NNB GenCo’s design management, its construction management, together with its application of relevant good engineering practice in the area of the prefabricated steel pool liner to the IRWST for Unit 1 at HPC.