- Site: Chapelcross
- IR number: 21-163
- Date: February 2022
- LC numbers: 11, 17
Executive summary
Purpose of Intervention
These Licence Compliance Inspections were carried out as part of a series of planned inspections for the Chapelcross (CHX) decommissioning site during 2021/22.
Interventions Carried Out by ONR
I carried out Licence Compliance inspections on CHX’s Licence Condition (LC) 11 and 17 arrangements and their implementation. I also held an update meeting with the CHX Safety Representatives.
Explanation of Judgement if Safety System Not Judged to be Adequate
N/A
Key Findings, Inspector's Opinions and Reasons for Judgements Made
From the documentation examined and the areas inspected, I found that CHX’s implementation of its LC11 (Emergency arrangements), and LC17 (Management Systems) arrangements were adequate.
Conclusion of Intervention
I judged that CHX’s implementation of its LC11 and LC17 arrangements as adequate in the areas inspected and I did not identify any significant regulatory concerns.