Executive summary
Purpose of Intervention
The purpose of this intervention was to ensure that Hunterston A power station is:
Demonstrating compliance with the life safety requirements of the Fire (Scotland) Act 2005.
Interventions Carried Out By ONR
This inspection assessed arrangements to support Life Fire Safety and sampled the implementation of those measures on site. Compliance was assessed using relevant ONR inspection guidance. This inspection consisted of examination of the licensee’s arrangements, meetings to assess implementation and management of Life Fire Safety and a site walkdown to review assets pertaining to Life Fire Safety.
Key Findings, Inspectors Opinions and Reasons for Judgements Made.
I examined the licensee’s Life Fire Safety arrangements, how they have been implemented and consider them to be adequate and in compliance with the Fire (Scotland) Act 2005.
Conclusion of Intervention.
I am content that the arrangements made under the Fire (Scotland) Act 2005 are adequate and implemented appropriately for the licensee’s activities.