Executive summary
Date(s) of inspection:
- June 2023
Aim of inspection
The purpose of the inspection was to cover the relevant themes for compliance against the requirements of CGD09/ADR.
Subject(s) of inspection
- Transport (Non-nuclear) Appropriate management system – Rating: Green
- Transport (Non-nuclear) Emergency arrangements – Rating: Cancelled
- Transport (Non-nuclear) Sub contract arrangements – Rating: Green
Key findings, inspector’s opinions and reasons for judgement made
This company supplies type A packages. The packages are manufactured by an industrial company wholly owned by Geovista, for supply to requesting entities. The request for supply of a package happens circa 5 times per year. The industrial company is inspected by HSE.
The type A packages supplied demonstrably meet the manufacture and testing requirements of CDG’09/ADR. The package’s use is outside the control of the company. Adequate information and certification is provided to purchasers. The company is its own design authority, and complies with requirements.
Conclusion
I believe this company to be low risk for supplying packages, and unless circumstances change or there is an incident do not require a compliance inspection for five years.