- Site: Chapelcross/Hunterston A
- IR number: 20-038
- Date: September 2020
- LC numbers: 22, 26, 28
Executive summary
Purpose of Intervention
These Licence Compliance Inspections were carried out as part of a series of planned inspections for the Chapelcross (CHX) and Hunterston A (HNA) decommissioning sites during 2020/21.
Interventions Carried Out by ONR
I carried out Covid-19 restart inspections on CHX’s and HNA’s Licence Condition (LC) 22, 26, 28 and conventional health & safety arrangements for control of restart operations and their implementation. In addition, I held on-site meetings with the CHX and HNA Safety Representatives.
Explanation of Judgement if Safety System Not Judged to be Adequate
N/A.
Key Findings, Inspector's Opinions and Reasons for Judgements Made
From the documentation examined and the areas inspected, I judged that CHX’s and HNA’s Covid-19 restart arrangements made under LCs 22, 26, 28, and for conventional health & safety for the control of restart operations and their implementation were adequate.
Conclusion of Intervention
No regulatory concerns were identified as a result of the inspection and future engagement will continue as detailed in the 2020/21 inspection plan.